Construction Technology and Quality Control of Double Layer Continuous Paving of Cement Stabilized Macadam Base

Authors

  • Jin Ma Wuzhong municipal construction management center Wuzhong, Ningxia, 751100, China

DOI:

https://doi.org/10.30564/jaeser.v3i3.2201

Abstract

The construction method of continuous paving of the upper and lower base of the water stable macadam base can improve the construction efficiency, overcome the quality problems of the traditional layered paving of the upper and lower base, such as untimely curing, slow construction, poor interlayer bonding, contraction joint and interlayer, so as to ensure the construction quality of the water stable macadam. It is also the promotion and application of new technology.

Keywords:

Highway and municipal engineering; Water stable double layer continuous paving; Construction technology; Quality control

References

[1] Technical rules for construction of highway pavement base (JTG / T f20-2015).

[2] Specification for field test of highway subgrade and pavement JTG e60-2008.

[3] Changsheng He. Construction and Research on ecological development mode of open pit mine in Plateau[J]. Mining research and development, 2019,39(07): 142-145.

[4] Shibo Sheng. Prospect of ecological construction of green mines in China[J]. Open pit mining technology, 2019, 34(03): 8-10.

[5] Xiaoming Wei, Lijie Guo, Xinzheng Chen, et al. Experimental study on cemented tailings filling in jinchanghe Polymetallic Mine[J]. Mining research and development, 2020, 40(06): 42-46.

Downloads

How to Cite

Ma, J. (2020). Construction Technology and Quality Control of Double Layer Continuous Paving of Cement Stabilized Macadam Base. Journal of Architectural Environment & Structural Engineering Research, 3(3), 26–28. https://doi.org/10.30564/jaeser.v3i3.2201

Issue

Article Type

Article